Provisions and contingent liabilities

Apply the IAS 37 tests to decide between a provision, a disclosed contingent liability or nothing, and measure provisions.

25 min7 exercisesMembers Save

You will be able to

  • Apply the three recognition criteria for a provision (IAS 37.14).
  • Distinguish provisions, contingent liabilities and contingent assets.
  • Measure a provision using expected value or most likely outcome, with discounting.
  • Contrast the IFRS threshold with US GAAP (ASC 450).

Related standards

IAS 37.14 · ASC 450

A provision is a liability of uncertain timing or amount — a warranty obligation, a lawsuit the entity expects to lose, a legal duty to clean up contamination. Under IAS 37.14 a provision is recognised only when all three conditions are met:

  1. A present obligation (legal or constructive) as a result of a past event. A legal obligation comes from a contract or law; a constructive obligation comes from an established pattern of practice or a published policy that has created a valid expectation in others (for example, a store that always refunds unhappy customers). The obligating event must already have happened — the sale of goods under warranty, the contamination caused.
  2. A probable outflow of resources — under IAS 37, "probable" means more likely than not (over 50%).
  3. A reliable estimate can be made. IAS 37 says this is almost always possible; only in extremely rare cases is a provision left out for this reason.

If the first condition is met but the outflow isn't probable — or there is only a possible obligation whose existence depends on uncertain future events — the item is a contingent liability. Contingent liabilities are not recognised; they are disclosed in the notes unless the possibility of an outflow is remote. Contingent assets (a lawsuit the entity expects to win) are never recognised until the inflow is virtually certain; they're disclosed when an inflow is probable.

Things that are not provisions: future operating losses (no past event), costs the entity can avoid by its own future actions (planned staff training, a decision to refurbish), and general "reserves for contingencies". A restructuring is provided for only when there is a detailed formal plan and those affected have a valid expectation it will happen — a board decision kept inside the boardroom isn't enough.

Measurement (IAS 37.36–40) is the best estimate of the amount to settle the obligation at the reporting date. For a large population of similar items (warranties) use the expected value — each outcome weighted by its probability. For a single obligation (one lawsuit) the most likely outcome is often the best estimate, adjusted if the other outcomes are mostly higher or lower. Where the effect of the time value of money is material, discount the expected cash flows; the provision then unwinds each year, and the increase is a finance cost (IAS 37.60).

Included with a Formula Quest membership

A membership includes the worked examples, all 7 graded exercises and the full curriculum. The foundations track, the first ledger lessons and the Northstar Trading case stay free.

References

Content review: answers and figures are checked by automated tests against the accounting engine, and the text has had an internal review against the standards; independent review by a qualified accountant is pending.